    济南地面找平的注意事项及流程
    来源:http://www.jndmzp.com   时间:2014-2-27 14:07:27

    1、地面找平的规范程序:
    Standardize the procedures of 1, the ground leveling:
    基层处理→找标高、弹线→洒水湿润→抹灰饼和标筋→搅拌砂浆→刷水泥浆结合层→铺水泥砂浆面层→木抹子搓平—铁抹子压遍→第二遍压光→第三遍压光→养护
    Primary treatment, find the elevation, elastic line, watering moist, plastering cake and marking ribs, mixing mortar, brush slurry with layers, laid with cement mortar layer, wood trowel rub flat iron trowel pressure again, second times the pressure of light, third times the pressure of light - curing
    2、将基层上的灰尘扫掉,用钢丝刷和錾子刷净、剔掉灰浆皮和灰渣层,用10%的火碱水溶液刷掉基层上的油污,并用清水及时将碱液冲净。
    2, the dust will be the basic level of the sweep, with a wire brush and chisel brush net, tick off the mortar skin and the ash layer, with 10% sodium hydroxide solution to brush off the oil base, and with water in the alkaline rinse.
    3、根据墙上的+1000mm水平线,往下量测出面层标高,并弹在墙上。
    3, according to the +1000mm horizontal line on the wall, to measure the surface elevation, and play on the wall.
    4、根据房间内四周墙上弹的面层标高水平线,确定面层抹灰厚度(不应小于20mm),然后拉水平线开始抹灰饼(5cm*5cm),横竖间距为1.5—2.0米,灰饼上平面即为地面面层标高。如果房间比较大,还须抹标筋。铺抹灰饼和标筋的砂浆材料配合比均与抹地面的砂浆相同。
    4, according to the room on the walls around the elastic surface elevation level, determine the surface layer plastering thickness (not less than 20mm), then pull line began to plaster cake (5cm*5cm), horizontal and vertical spacing of 1.5 - 2 meters, ash cake plane is on the ground surface elevation. If the room is relatively large, but also reinforcement. Ratio are the same with the mortar with the ground with mortar plastering cake shop and bar.
    5、搅拌砂浆,用搅拌机进行搅拌,颜色必须一致。
    5, mixing mortar, use a blender for mixing, color must be consistent.
    7、铺设水泥砂浆前,涂刷水泥浆一层(随刷随铺面层砂浆)。
    7, the laying of the cement mortar, coating of cement slurry layer (with the brush with the pavement layer mortar).
    7、在涂刷完水泥砂浆后,铺水泥砂浆,并在灰饼之间将砂浆铺均匀。
    In 7, after brushing finished cement mortar, cement mortar, and the ash cake will spread evenly between mortar.
    8、木抹子刮平后,迅速用铁抹子压遍,直到出浆为止。面层砂浆初凝后,用铁抹子压第二遍,表面压平压光。在水泥砂浆终凝前进行第三遍压光,必须在终凝前完成。 并随时用2米靠尺检查其平整度。
    8, Ki Ko scraped, quickly with a trowel pressure again, until the mortar. The surface layer of mortar after the initial setting, with a trowel pressure second times, surface flattening pressure light. Third times the pressure of light in the final set of cement mortar, must be completed before the final setting. And at any time on foot by 2 metres to check its smoothness.
    9、完工后24小时(地面压光),铺锯末或其他材料覆盖洒水养护,保持湿润,养护时间不少于7天,抗压强度达5Mpa时才能上人。
    9, after the completion of 24 hours (ground pressure), shop sawdust or other material coverage of water conservation, moist curing time, not less than 7 days, before people compressive strength reaches 5Mpa.