    家装自流平施工工艺流程
    来源:http://www.jndmzp.com   时间:2015-12-28 16:47:35
    1、基底处理—基层必须洁净、干燥、坚固(强度大于C20)没有结构上的缺陷。
    1, the base must be clean, dry, strong (strength than C20) no structural defects.
    2、界面剂涂刷—采用优地UD-CU18多功能界面剂,将界面剂按1:1加水混合均匀,然后用软刷子或是喷壶将界面剂涂刷到准备好的基层表面,涂刷均匀避免产生积液。界面剂的用量视基层具体情况而定,一般要采用二遍滚涂。约2-3小时后开始自流平施工。
    2, brushing interfacial agent with the advantage of UD-CU18 multi-function interface agent, the interface agent in a 1:1 water mixing, and then use soft brush or a watering can to besmear brushs interfacial agent to prepared on the surface of the base layer, coating evenly to avoid effusion. The amount of the interface agent depends on the specific circumstances of the basic level, the general need to use two times roll coating. About 2-3 hours after the beginning of self leveling construction.
    3、搅拌自流平—将6升的水导入适当容器然后将UD-50自流平水泥25kg/包,缓慢倒入,边倒入边用强制搅拌器搅拌1-2分钟,静置1分钟后,继续强制搅拌一分钟。
    3, stirring self leveling - the 6 liters of water into the appropriate container and then UD-50 self leveling cement 25kg/ bag, slowly into the edge of the edge into the edge with a forced mixer for 1-2 minutes, after 1 minutes, continue to force one minute to force.
    4、摊铺自流平—自流平搅拌后,一次性将其倒在地面上,摊铺的工作不能存在间歇,直至将整个地面都摊平为止(大面积施工时,建议采用自流平搅拌机及泵送机械施工),将浆倒入施工区域均匀铺开,用专用齿口刮板辅助自流平的流动,刚施工好的区域避免阳光直射和强风。
    4, paving leveling self leveling mixing, one shot on the ground, paving the work can not exist intermittent, until the whole ground leveling up (a large area of construction, it is recommended to use self leveling mixer and pumping machinery construction), the slurry into the construction area evenly spread, with special teeth mouth scraper auxiliary flow, just the construction of a good area to avoid direct sunlight and strong wind.
    5、辅助找平后,立即用消泡滚筒滚扎地面,以排出自流平浆体中的空气。
    5, assist and immediately used the defoaming drum rolling ground, to discharge the air in the self leveling mortar.
    6、在自流平地面可行走时,可在混凝土结构的伸缩缝处用切割机切出3mm的伸缩缝,此伸缩缝应采用具有弹性的结构填缝胶填充。
    6, in self leveling floor feasible travel time can be in the expansion and contraction of the concrete structure joints with a cutting machine cutting 3mm expansion joints, the telescopic joint with elastic structural sealant filling should be adopted to.
    7、面层铺装—在室温20℃的情况下,摊平的自流平在3-4小时后即可在其上行走,地面的干燥时间取决于自流平的厚度及外界条件,一般3-5天即可铺地板或地毯。若自流平的湿度大,干燥条件差,则干燥时间要延长。铺设其他地板材料时应遵守生产厂家的要求进行。
    7, surface layer pavement - at room temperature 20 degrees Celsius, the leveling of the self leveling in 3-4 hours after walking on the ground, the drying time depends on the thickness of self leveling and outside conditions, generally 3-5 days to shop floor or carpet. If the self leveling humidity, dry condition is poor, the drying time should be extended. The laying of other floor materials should comply with the requirements of the manufacturer.