    地面找平施工工艺、流程及验收标准
    来源:http://www.jndmzp.com   时间:2017-10-17 17:31:44
    1、地面找平的规范程序:
    1. The standard procedure of ground leveling:
    基层处理→找标高、弹线→洒水湿润→抹灰饼和标筋→搅拌砂浆→刷水泥浆结合层→铺水泥砂浆面层→木抹子搓平→铁抹子压遍→第二遍压光→第三遍压光→养护

    To find the base elevation, elastic line, water wet, plastering cake and marking ribs, mixing mortar, cement slurry with brush layer and surface layer of cement mortar, with wood trowel trowel, rolling pressure, the over second times, third times the pressure of light pressure of light - curing

    济南地面找平

    2、将基层上的灰尘扫掉,用钢丝刷和錾子刷净、剔掉灰浆皮和灰渣层,用10%的火碱水溶液刷掉基层上的油污,并用清水及时将碱液冲净。
    2, the primary dust swept away, with a wire brush and chisel brush net, tick off the skin and ash mortar layer, with 10% caustic soda solution to brush off oil base, and promptly rinse with water solution.
    3、根据墙上的+1000mm水平线,往下量测出面层标高,并弹在墙上。
    3. According to the +1000mm horizontal line on the wall, measure the elevation of the surface layer and bounce it on the wall.
    4、根据房间内四周墙上弹的面层标高水平线,确定面层抹灰厚度,然后拉水平线开始抹灰饼,横竖间距为1.5—2.0米,灰饼上平面即为地面面层标高。如果房间比较大,还须抹标筋。铺抹灰饼和标筋的砂浆材料配合比均与抹地面的砂浆相同。
    4, according to the room around the wall playing surface elevation level, determine the thickness of surface layer plastering, and then pull the horizontal line to horizontal spacing of 1.5 plaster cake, - 2 meters, ash cake is the ground surface elevation plane. If the room is large, it must also wipe the mark. The mixing ratio of mortar material for plastering cake and standard reinforcement is the same as that of plastering ground mortar.
    5、搅拌砂浆,用搅拌机进行搅拌,颜色必须一致。
    5, mixing mortar, stirring with mixer, the color must be consistent.
    6、铺设水泥砂浆前,涂刷水泥浆一层。
    6, before laying cement mortar, brushing cement paste layer.
    7、在涂刷完水泥砂浆后,铺水泥砂浆,并在灰饼之间将砂浆铺均匀。
    7, after brushing cement mortar, laying cement mortar, and in the mortar between the mortar evenly paved.
    8、木抹子刮平后,迅速用铁抹子压遍,直到出浆为止。面层砂浆初凝后,用铁抹子压第二遍,表面压平压光。在水泥砂浆终凝前进行第三遍压光,必须在终凝前完成。 并随时用2米靠尺检查其平整度。
    8, wood trowel scraping, quickly with trowel pressure again, until the mortar. The surface layer of mortar setting, with iron float pressure second times, the surface pressure light pressure. Third times of calendering before cement mortar final solidification must be completed before final solidification. And check the evenness with 2 meters at any time.