    地面找平施工工艺
    来源:http://www.jndmzp.com   时间:2017-10-27 15:24:49
    1、地面找平施工之基底处理。在涂刷墙面乳胶漆、铺贴墙地砖之前,我们一定要做好基底的处理。有一些工人在施工的时候会在这方面偷工减料,轻则会造成墙面的不平整,乳胶漆涂刷后有一些色差,如果严重就会导致乳胶漆变色脱落,或是瓷砖粘贴不牢。所以基层的工作要做好。

    1. Ground treatment of ground leveling. Before brushing the wall latex paint and paving the wall and floor tiles, we must do well the basement treatment. Some of the workers will cut corners in this area at the time of construction, the light will cause the wall roughness, latex paint and some color, if serious, will cause the color emulsioni paint falls off, or tile loose adhesion. Therefore, grass-roots work should be done well.

    地面找平哪家好

    2、地面找平施工之如何处理地面找平。自流平找平地面处理施工,它的在于:不起砂,不接缝,不起尘;施工厚度也很薄,一般在2~5毫米左右,施工之后干的也比较快,能缩短工期。适用范围:不能做局部,要整个房间做找平。
    2, ground leveling construction how to deal with ground leveling. Self leveling leveling ground construction, it lies in: no sand, no seams, not dust; construction thickness is very thin, generally about 2~5 mm, after the construction is also faster, can shorten the construction period. Scope of application: can not do local, to make the whole room leveling.
    3、根据房间内四周墙上弹的面层标高水平线,确定面层抹灰厚度,然后拉水平线开始抹灰饼,横竖间距为1.5—2.0米,灰饼上平面即为地面面层标高。如果房间比较大,还须抹标筋。铺抹灰饼和标筋的砂浆材料比均与抹地面的砂浆相同。
    3, according to the room around the wall playing surface elevation level, determine the thickness of surface layer plastering, and then pull the horizontal line to horizontal spacing of 1.5 plaster cake, - 2 meters, ash cake is the ground surface elevation plane. If the room is large, it must also wipe the mark. The mortar material of plastering cake and standard bar is the same as that of plastering ground mortar.
    4、搅拌砂浆,用搅拌机进行搅拌,颜色必须一致。铺设水泥砂浆前,涂刷水泥浆一层。在涂刷完水泥砂浆后,铺水泥砂浆,并在灰饼之间将砂浆铺均匀。
    4, mixing mortar, stirring with mixer, the color must be consistent. Before laying cement mortar, coat a layer of cement paste. After brushing the cement mortar, the cement mortar is laid, and the mortar is evenly laid between the ash cakes.
    5、木抹子刮平后,迅速用铁抹子压遍,直到出浆为止。面层砂浆初凝后,用铁抹子压第二遍,表面压平压光。在水泥砂浆终凝前进行第三遍压光,必须在终凝前完成。并随时用2米靠尺检查其平整度。
    5, wood trowel scraping, quickly with trowel pressure again, until the mortar. The surface layer of mortar setting, with iron float pressure second times, the surface pressure light pressure. Third times of calendering before cement mortar final solidification must be completed before final solidification. And check the evenness with 2 meters at any time.
    公司全方位服务于客户,以质量上乘、价格合理和完善的售后服务与客户携手奋进,共同发展。质量保证,欢迎咨询洽谈。
    The company serves the customers all round, with high quality, reasonable price and perfect after-sales service and customer hand in hand, and common development. Quality assurance, welcome to consult and negotiate.