    地上找平用的办法
    来源:http://www.jndmzp.com   时间:2018-9-14 14:49:37
    地上找平用的办法
    Ways of leveling the ground
    1. 地上找平用的办法—机器研磨加石膏找平。不增高地上 ,施工后2h,就可以在上面走动(施工) ,施工3天就可以铺木地板 ,施工方便(每户只需一天)价位又实惠,比水泥找平缓自流平要优惠的多。
    1. method of leveling on the ground - machine grinding and plaster leveling. No increase in height, 2 hours after the construction, you can walk on (construction), construction can be laid in 3 days wood flooring, construction convenience (only one day per household) price and affordable, than the cement leveling slowly more preferential.
    2. 地上找平用的办法—水泥砂浆找平。增高地上低2公分 ,施工后要3天可以在上面踩(施工) ,施工竣工今后要等低15天今后铺木地板 ,价位适中。
    2. method of leveling on the ground - cement mortar leveling. Increase the height of the ground 2 cm lower, three days after the construction can be stepped on (construction), the completion of the construction of the future to wait for 15 days to lay wood flooring, moderate price.
    3. 地上找平用的办法—自流平找平。去房间的高点 ,施工今后24h不能进人 。施工后和水泥差不多也要15天今后铺木地板 ,价位高。
    3. method of leveling on the ground self leveling leveling. To go to the high point of the room, 24h can not enter people after construction. After construction and cement almost 15 days later, wood flooring will be priced at a high price.
    地上找平用的过程?
    The process of leveling on the ground?
    1、地上找平用的过程—地上底层处理?。在进行施工之前,同样是需求对地上底层进行处理的,以确保地上空鼓、起块等缺点现已被修补或根除。并确保地上底层整理洁净,没有施工妨碍。此外,主张需求对已完结的木制品的根部包扎,对室内原有设备的根部包扎或用资料进行隔挡。
    1. The process of leveling on the ground? Before construction, it is also necessary to deal with the above ground floor to ensure that the shortcomings of the above ground, such as bulging, have been repaired or eradicated. And ensure that the ground floor is clean and clean, and there is no construction obstruction. In addition, it advocates the need to wrap the roots of finished woodwork, wrap the roots of the original indoor equipment or block with information.
    2、地上找平用的过程—标高抹灰饼。依据地上铺贴饰材的种类厚度和完结面标准线断定找平厚度,一般面层抹灰厚度不小于20mm,在墙面弹出找平控制线。依据找平控制线沿墙四周抹灰饼,灰饼巨细一般为5x5cm巨细,横竖距离为1.5—2.0米,灰饼上平面即为地上面层标高。假如房间比较大,还须抹标筋。铺抹灰饼和标筋的砂浆资料比均与抹地上的砂浆相同。

    2. The process of leveling on the ground - elevation plaster. The leveling thickness is determined according to the type and thickness of the decorative materials on the ground and the standard line of the finish surface. Generally, the plastering thickness of the surface is not less than 20 mm, and the leveling control line pops up on the wall. According to the leveling control line plastering around the wall, the size of the cake is generally 5 x 5 cm, the vertical distance is 1.5-2.0 meters, the surface of the cake is the elevation of the ground surface. If the room is large, it must also be marked with tendons. The mortar data of the plaster cake and the standard reinforcement are the same as those of the mortar on the floor.

    济南地面找平

    3、地上找平用的过程—刷水泥浆。水泥浆的效果是为了使得水泥沙浆和地上的联接严密。水泥浆需求依照1:0.5的份额制造,调制好后,用扫帚等工具涂刷到地上,构成结合层。
    3. The process of leveling on the ground - brush the cement slurry. The effect of cement slurry is to make cement mortar and ground connection tighter. The cement slurry needs to be manufactured in accordance with the 1:0.5 share. After being prepared, the cement slurry is coated on the ground with broom and other tools to form a bonding layer.
    4、地上找平用的过程—铺水泥砂浆。在涂刷完水泥砂浆后,铺水泥砂浆,泥砂浆比为水泥:砂=1:2,应拌和均匀。满铺水泥砂浆后用长木杠拍实搓平,使砂浆与底层结合密实。
    4. The process of leveling on the ground - cement mortar. After brushing the cement mortar, lay the cement mortar, the mortar ratio is cement: sand = 1:2, should mix evenly. After the cement mortar is fully covered, it will be rubbed with the long wooden bar to make the mortar and the bottom layer compact.
    5、地上找平用的过程—外表亚光处理。外表压光分两次进行。在水泥砂浆凝聚稍有反水,人踩上去有足迹,但不下陷时,撒干水泥面后用铁抹子压光,从边角到大面,次序加力压实抹光,九正家居网提示待水泥砂浆终凝前进行第二遍压光,用铁抹子将压光留下的抹纹压平、压实、压光。并随时用靠尺查看平整度。
    5. The process of leveling on the ground - Surface matte treatment. The external pressure is divided into two parts. In cement mortar condensation slightly anti-water, people step on footprints, but not subsidence, dry the cement surface with iron plaster after pressing, from the corner to the large surface, the order of compression smoothing, nine positive home net prompt to wait for cement mortar final set before the second calendering, with iron plaster calendering, compaction, calendering. And use the ruler to check evenness.
    6、地上找平用的过程—竣工维护。面层压光4h后,在面层铺锯末或其他资料覆盖浇水维护,保持湿润,维护时刻不少于7天,抗压强度达5Mpa时才干上人。水泥砂浆找平法施工,要求面层和底层粘结牢固,不该空鼓;外表应密实压光,不允许有裂缝、脱皮、起沙等缺点。
    6. The process of leveling on the ground - completion and maintenance. After 4 hours of surface calendering, cover the surface with sawdust or other materials for watering maintenance, keep wet, maintain time not less than 7 days, compressive strength up to 5 Mpa before drying. The cement mortar leveling method requires that the surface and bottom layers are firmly bonded and should not be empty, and the surface should be compact and smooth, not allow cracks, peeling, sand and other shortcomings.
    小马识途地面找平,济南地面找平对本站有兴趣的朋友可以关注我们http://www.jndmzp.com
    The pony knows the way to leveling the ground, Jinan leveling the ground interested friends can pay attention to our http://www.jndmzp.com

鲁公网安备 37148202000237号